2015 Spring Work Begins on Armory

Lots of folks are curious about the status of the Armory. After months of inactivity, work began on a few general improvements about a month ago. I spoke with Mike with J&M earlier this year and he gave me a rundown on the goals of the current push:

  • Daylighting basement windows. The roughly 7,000 sq. ft. below-grade spaces facing Reserve Street will be getting slightly larger glazed openings.
  • Enlarging window wells. The old window wells were pretty small, so workers have excavated a large trench that will slope up toward ground level to create a berm that allows more light to reach the windows.
  • Retaining wall. The top of the berm will feature an 18″ retaining wall with deep footings. This will keep water and other unwanted things out of the window wells.
  • Drainage system. This will add to the protection of the below-grade space from potential flood events.
  • Seismic reinforcement. Due to the age of the structure, additional work will helped stabilize walls in the event of any seismic activity.

I got a tour from Gene, one of the workers on site. He mentioned how much everyone enjoys working in the space, surrounded by history and the amazing natural light. Here are a few photos showing the interior spaces and a few exterior details. Thanks to Mike and Gene for helping answer some questions; neighbors are understandably curious.

Armory 4_17_1517

2nd Floor NE space showing morning sunlight. This level, like the Main Floor and day-lit basement contains about 7,000 sq. ft.

Armory 4_17_1502

NE corner showing excavation for light well (against building) and retaining wall (trench at right adjacent to pavement). Forms are no in place and concrete should be poured in coming weeks.

Armory 4_17_1515

14,400 sq. ft. Drill Hall, roughly 80′ X 180′ of unobstructed space, showing the original bowstring trusses supporting the arched middle roof. The lower left wall shows openings into the rear section of the building, that originally housed the National Guard stables and horses.

Armory 4_17_1504

East wall looking toward the rear of the building. The front section contains approximately 21,000 sq. ft. on three levels, the middle section with 14,400 sq. ft., and the rear single-level section with approximately 5,000 sq. ft.

DSCN2198

Interior panorama of rear single-level space, originally housing the stables for the Idaho National Guard.

DSCN2189

Original bowstring trusses (above) and detail of the roof framing and structure, which includes repurposed dimensional-lumber concrete board forms used in the 1937 construction. The second floor wings were added in the 50s, when workers had access to plywood for forms. This is why the texture and original colors were different from early ours to later pours.

DSCN2188

Roof detail showing repurposed 1937 concrete board forms. This was the depression, so nothing was wasted.

IMG_0568

NE Corner showing board forms and concrete prep. Owner characterized finished retaining walls as “Eighteen inches above grade.”

IMG_0566

View SE from west corner of Armory showing footings for retaining wall.

IMG_0569

View west from NE corner showing forms for retaining wall.